Rooftop HVAC units on a commercial distribution center — illustrative placeholder.

Amazon · Distribution Center, Lawrence Township, NJ

35 rooftop units, set by helicopter

Scope
Plan & spec for HVAC across a new 400,000 sq ft facility.
Challenge
Placing 35 units on a condensed timeline inside a fixed cost structure.
Approach
Industrial helicopter installation chosen over crane lift to save time and control cost. Weather forced last-minute revisions; permitting and scheduling were re-sequenced around the forecast.
Result
Completed to the revised plan without incident, connected and commissioned inside the schedule.
“Four Quarters' expertise and problem-solving abilities enabled us to avoid problems and stay on schedule.” General contractor, Amazon distribution center
Refrigerated food-storage room with produce and overhead cooling — illustrative placeholder.

Taylor Farms · Food Processing, Swedesboro, NJ

A food-grade plant that never stopped running

Scope
Plan & spec for HVAC and plumbing.
Challenge
Install and commission a large rooftop unit in an existing structure while the facility stayed in production.
Approach
Procurement coordinated around specialty equipment and installation protocols that hold USDA food-grade compliance.
Result
Delivered to strict government guidelines, on schedule, with the plant operating throughout.
“Scheduling and installation logistics made a very complex project run right on schedule. Their proactive communication made everything run smoothly.” General contractor, Taylor Farms plant
Modern medical office building — illustrative placeholder.

Jefferson Imaging Center · Washington Township, NJ

MRI venting through a space that wasn't there

Scope
HVAC plan & spec, coordinated with an MRI installation.
Challenge
Specialty venting demanded large, intricate ductwork in a very small space on a compressed schedule.
Approach
Piped in a chiller and relocated much of the refrigerant piping to the roof, sequenced so neighbouring tenants kept trading.
Result
Every phase delivered to plan and on time.
“There was a lot of anxiety because of the complexity of the installation. Thanks to Four Quarters the job went smoothly, and everyone was able to relax.” General contractor, Jefferson Imaging Center
Giant Food Store exterior.

Giant Food Store · Broomall, PA

A full plumbing package, underground up

Scope
Complete plumbing package for a supermarket build.
Challenge
Underground sanitary and storm, domestic water, gas piping, kitchen and bathroom fixtures, and a Jet Vac condensation system — all interdependent.
Approach
Manpower staffed to hit every deadline, with supervision dedicated to coordinating field work across trades.
Result
Completed to code and to owner specification.
“This was a project that called for a wide range of expertise and coordination. Four Quarters made it all happen.” General contractor, Giant Food Store
Rooftop piping runs on supports at the National Refrigerants facility in Bridgeton, NJ.

National Refrigerants, Inc. · Bridgeton, NJ

Four piping systems, one unforgiving schedule

Scope
Water, sanitary, compressed air and gas piping for the facility.
Challenge
An intense construction schedule, with four piping disciplines to land inside it.
Result
Finished on time — and the client's one-word review of the job was “fantastic.”

Our Certifications

Credentialed for the work we take on

EPA 608 Certified

Federal certification for the safe handling of refrigerants.

NATE Certified

North American Technician Excellence — the HVAC industry's leading technician standard.

A2L Ready

Trained on the new low-GWP A2L refrigerants now entering the market.

HVAC Master's License

Licensed at master level for heating and cooling work.

Heat Exchanger Expert

Specialist diagnosis and service of heat exchangers.

Our Valued Business Partners

The teams we build alongside

A&E Construction
ARCO National Construction
Blue Rock
FCL Builders
Greek
Iron Hill Construction Management
North Star
Peak
Penntex Construction
R.C. Andersen
Trane
Tricon
Whitesell

Let's discuss your project

Tell us about the schedule, the site and the scope. We'll tell you straight whether we're the right team — and how we'd approach it.